Current Year Summary of Completeness
October 1, 2013 through September 30, 2013
The average completeness metric value (number of samples / expectation*) by month
FY2014 Quarter 1

  Oliktok Point, Alaska (OLI)
Termination date maxdate Expected (mode)
value
Month QTR average YTD average Number of
Missing
Days
Oct Nov Dec
Datastream name . 30DEC2013 1440 1.00 0.97 0.97 0.98 0.98 2
oligndrad60sM1.b1
oliirt200msM1.a1 . 30DEC2013 432E3 1.00 0.97 0.96 0.98 0.98 2
oliirtM1.b1 . 30DEC2013 1440 1.00 0.97 0.96 0.98 0.98 2
olimetM1.b1 . 30DEC2013 1440 1.00 0.97 0.97 0.98 0.98 2
olimfrsrM1.b1 . 08NOV2013 4086 1.00 0.97 . 0.98 0.98 0
olimplpolfsM1.b1 . 30DEC2013 8640 1.00 0.97 0.95 0.97 0.97 2
olimwr3cM1.b1 . 30DEC2013 7926 1.04 1.05 1.07 1.05 1.05 4
oliskyrad60sM1.b1 . 30DEC2013 1440 1.00 1.00 0.97 0.99 0.99 1
olivceil25kM1.b1 . 30DEC2013 5400 1.00 0.67 0.97 0.88 0.88 2
Site average . 30DEC2013 432E3 1.00 0.95 0.98 0.98 0.98 17

(*Expectation = statistical mode of the number of samples per file per data stream from reference period of operational history).